Argonaut

Case studySeiyun, Yemen

Kharir Development Phase-I, Block 10 – BPU

Kharir Development Phase-I, Block 10 – BPU

Seiyun, Yemen

Table of contents

Sectors

  • Oil & Gas

Expertise

  • Electrical
  • Mechanical
  • HVAC

Capabilities

  • Engineering
  • Procurement
  • Construction

Clients

  • Total E&P - Yemen
  • PETROJET

Project Name

Kharir Development Phase-I, Block 10 – BPU

Location

Seiyun, Yemen

Project Owner

Total E&P - Yemen

Main Contractor

Petrojet (Petroleum Projects and Technical Consultations Company)

Project Consultant

Enppi (Engineering for Petroleum and Process Industries)

Project Scope

Design, fabrication, supply, installation, testing, adjustment, balancing and warranty of HVAC systems including:

  • Air-cooled condensing units (450kW+ cooling capacity)
  • Air handling units (17,140 l/s supply flow, 450kW cooling capacity)
  • Air cooled packaged units (7,480 l/s supply flow, 220kW cooling capacity)
  • Condensing split units (6-70kW capacity range)
  • Air handling split units (545-5,285 l/s flow range)
  • Ductwork and air outlets
  • Exhaust fans
  • Terminal duct heaters
  • Motor control center
  • Automatic control system
  • Pressurization system
  • Battery room ventilation system

Industry Classification

Oil and Gas / Petrochemical Industries

Recognition was given for Argonaut's valuable contributions and dedicated cooperation on mechanical and electrical work. The company completed their assigned tasks in a timely, quality manner during the construction, fabrication, and pre-commissioning phases of the Basement Process Unit (BPU) project, spanning December 2009 to October 2010.
A. Shatla and T. A. Azeem / S. A. Dayeem, Total